|
| |
CASE HISTORY 992203-02
|
SITE: |
Petroleum contaminated insitu soils and waters. |
|
BIODEGRADED MATERIAL: |
Gasoline |
|
SITE SURVEY: |
Site and geological surveys had revealed the sources of
contamination were 4 UST’s from a former gas station located at the
southwest corner of this vacant site. Groundwater was found at a depth of
17 feet below the surface and the groundwater ran up against the wall of
the underground subway structure. Samples were obtained and the initial
laboratory samples revealed that the levels of contamination were
actionable. The
soils encountered were primarily sand, silt, clay, and gravel. |
|
METHOD: |
Insitu bioremediation was selected to enable the site
to be cleaned-up and put back into productive use with the least amount of
disruption to the adjacent property, the clients business and the site
itself. 16 monitoring wells were installed, each 2-inch slotted PVC, to an
average depth of 20 feet. These were used to further define the project on
and off site, amend the existing site assessment reports, to deliver
remedial products, and to monitor and test the site during and after
completion of the remedial project. A bio infiltration system was also
installed. This consisted of installing 14 rows of 4 inch flexible PVC.
Each row in the matrix was approximately 200 feet long and installed
alternatively at approximately 5-10 feet deep. The matrix was spaced
equally across the entire site. The H-10™ product placement was made via
a matrix of borings. Once the Bio Rem H-10™ product was applied, there
was no other addition of oxygen sources or other nutrients needed to
remediate the site. The contaminated area was then tested after
remediation. Readings were taken at periodic intervals with the use of a
photo ionization detector (PID). The PID readings were taken from the
borings/TVMPs placed in and around the contaminant plume. As readings
indicated non-detect levels, soil and water samples were taken from those
areas showing no contamination and sent for formal analysis by a
certified, independent laboratory. The NYSDEC allowed the closure of all
monitoring wells in the area where test results confirmed no contamination
3 consecutive times. There was residual contamination, which had migrated
down gradient from the source area. Treatment was required to continue
down gradient until the residual migrated contaminants in wells MW-6,
MW-8, and MW-9 (MW-8 and MW-9 were also know as B-8 and B-9) were
biodegraded below actionable levels.
The treatment with Bio Rem H-10™ bacteria
began on May 1999 to June 1999. The samples were analyzed progressively in
July 2000 by an independent lab confirmed that the site is below NYSDEC
action levels for soil and groundwater. The results of the laboratory analysis were
obtained using U.S. EPA Method 602 as required by the NYSDEC. |
|
COMMENTS: |
The NYSDEC has issued a "no further action"
status for this site. The property has no tie to a disposal site,
eliminating any future liabilities. After remediation a new Walgreen’s
Drug Store was built on this location. |
Map

|